Don Valley Engineering awarded major vibrating screen order

Don Valley Engineering Co. Ltd have received an order for 10 bespoke vibrating screens for the Hemerdon Tungsten and Tin Project, which is located near to Plymouth in South West England. 

The order was received from GR Engineering Services (UK) Ltd, EPC contractors for the project, and is said to be one of the most significant screen orders placed in the UK in recent years.

Design work on the screens has commenced, and delivery will progress as required by the project. 

 

The Hemerdon mine is being developed by Wolf Minerals (UK) Ltd.

 